Thessaloniki Metro: Extension request by the contractor until March 2025 “if no solution is reached”
- Written by E.Tsiliopoulos
A surprising announcement regarding an extension request -until March 2025- has been made by the construction consortium (AIASA) for the never-ending project of Thessaloniki Metro.
As the Chairman of Attiko Metro, Mr. Nikos Tachiaos revealed while speaking at a conference in Thessaloniki, the contractor has submitted a request to Attiko Metro for an extension of the overall project deadline until March 2025 (and more particularly by 1,567 calendar days), provided that the project proceeds at the current pace.
It is reminded that the solution that has been chosen is the preservation of the antiquities. For his part, Mr. Tachiaos assured that Thessaloniki will have a completed Main Line with an operational Venizelou Station by April 2023.
Tagged under
Related items
-
€1.6 Billion to Fund 352 Projects Across Attica
-
The passport of the Chinese woman who has been missing for four months was found torn in the Galatsi Grove.
-
Greek-American matchmaker charges $5,000 a month to find love in New York
-
The iconic GREGY project at the Hellenic-American Chamber of Commerce Conference at the TIF
-
Thessaloniki: Two Afghanis under scrutiny for the fall of a 15-year-old from a hotel -
Latest from E.Tsiliopoulos
- €1.6 Billion to Fund 352 Projects Across Attica
- The passport of the Chinese woman who has been missing for four months was found torn in the Galatsi Grove.
- Greek-American matchmaker charges $5,000 a month to find love in New York
- The iconic GREGY project at the Hellenic-American Chamber of Commerce Conference at the TIF
- Thessaloniki: Two Afghanis under scrutiny for the fall of a 15-year-old from a hotel -