Over 50% of TAP pipes in Greece is in the ground

Over 50 percent of the Trans Adriatic Pipeline (TAP) in Greece (276km) has been placed in the ground and backfilled, while more than 95 percent of the line-pipes for the Greek section have been delivered to the ports of Kavala, Thessaloniki and Alexandroupolis, TAP Country Manager for Greece, Katerina Papalexandri, said at the 2nd Thessaloniki Summit.