The construction of the, 550 km long, Greek section of the TAP gas pipelinefrom the Ebro Gardens to the Greek-Albanian border, in Kristalopigi, Kastoria, will be completed, in November 2018.

Published in Greece
Friday, 13 October 2017 11:28

Over 50% of TAP pipes in Greece is in the ground

Over 50 percent of the Trans Adriatic Pipeline (TAP) in Greece (276km) has been placed in the ground and backfilled, while more than 95 percent of the line-pipes for the Greek section have been delivered to the ports of Kavala, Thessaloniki and Alexandroupolis, TAP Country Manager for Greece, Katerina Papalexandri, said at the 2nd Thessaloniki Summit.

Published in Greece
Tagged under

Trans Adriatic Pipeline (TAP) AG on Friday announced a one-million-euro initiative for funding Master's degree programmes in the energy sector, offered by the University and the Technological Educational Institute (TEI) of Western Macedonia ? the Prefecture's two tertiary education institutions. The investment is implemented in the context of the collaboration between TAP and the Bodossaki Foundation.