TAP Pipeline: The land returns to its owners in Greece, Albania & Italy
- Written by E.Tsiliopoulos
The land reclamation process in Albania, Greece and Italy has already taken place or is currently nearing 97% of the total TAP gas pipeline route, according to a joint venture managing the project.
TAP had to bind the land along the pipeline route in order to allow the pipeline and associated infrastructure to be constructed and operated.
This process, known as the Land Acquisition (LEA) process, is conducted in accordance with the European Bank for Reconstruction and Development (EBRD) international standards.
The project affects approximately 22,590 plots of land: 10,300 in Greece, 12,100 in Albania and 190 in Italy.
Tagged under
Related items
-
Greece moves to become Southeast Europe’s first carbon storage hub
-
Giannis Antetokounmpo says Heat provide best route to another NBA title
-
Mitsotakis says under-15s should be banned from major social media platforms, warns of AI's "extreme" risks
-
Marco Rubio made a reference to the murder of Vagia Nestora - "She was executed because her daughter dared to run for public office"
-
Greek banks have liquidity ready to fuel economic growth
Latest from E.Tsiliopoulos
- Greece moves to become Southeast Europe’s first carbon storage hub
- Giannis Antetokounmpo says Heat provide best route to another NBA title
- Mitsotakis says under-15s should be banned from major social media platforms, warns of AI's "extreme" risks
- Marco Rubio made a reference to the murder of Vagia Nestora - "She was executed because her daughter dared to run for public office"
- Greek banks have liquidity ready to fuel economic growth